Hamara School, Aligarh - Building Project

AEEF is proud of it’s significant contribution to construction of the new building for Hamara School. This project is designed to benefit approximately 1,100 children from underprivileged families, specifically focusing on ensuring that 50% of the beneficiaries are girls.

  • Total Site Area - 3,372 sq. yd (~30,348 sq. ft.)
  • Land Cost and Registration - ~₹1.32Cr
  • Date of Land Purchased - May 2023
  • Location of School - Nagla Bhai Beg, Aligarh (Approximately 3km from JNMC, AMU)

Total Build Area - 12,743 sq. ft.

Ground Floor Area - 11,926 sq. ft. & Porch Area - 817 sq. ft No. of classrooms –6, Principal Office, Office, Multipurpose Hall, Store rooms, Toilets for Boys & Girls

Budget Required - ₹1,65,65,900 (~USD $1,86,583 )*

Total Build Area - 12,743 sq. ft x 1300 per sq. ft

Seating Capacity - 270

  • In Phase 1, Class I to V.
  • Each class will have 45 students enrolled.

Expected Completion March 2026

The Foundation Excavation was on 13 Feb, 2025.

Total Build Area - 11,926 sq. ft.

First Floor Area - 11,926 sq. ft. No. of classrooms –9, Two Staff rooms (Male/Female), Computer Lab, Toilets for Boys & Girls, Store rooms.

Budget Required - ₹1,55,03,800 (~USD $174621)*

Total Build Area - 11,926 sq. ft x 1300 per sq. ft

Seating Capacity - 405

  • In Phase - 2, Class I to X.
  • Each class will have 45 students enrolled.

Expected Completion December 2026

The Foundation Excavation was on 13 Feb, 2025 Phase - 1, Expected Completion March 2026.

Total Build Area - 12,506 sq. ft.

Second Floor Area - 11,926 sq. ft. & Third Floor (Mumty Area) - 580 sq. ft.

No. of classrooms –9, Science Lab, Library, Store rooms, Toilets for Boys & Girls

Budget Required - ₹1,65,65,900 (~USD $1,86,583 )*

Total Build Area - 12,506 sq. ft x 1300 per sq. ft

Seating Capacity - 270

Expected Completion March 2027

  • The Foundation Excavation was on 13 Feb, 2025.
  • Phase - 1, Expected Completion March 2026.
  • Phase - 2, Expected Completion December 2026.